Difficulty: Easy
Correct Answer: 160
Explanation:
Introduction / Context:
 This uses the man-days concept with a very short target time. If the total man-days are fixed for a given job, reducing the days to a fraction requires increasing the number of men proportionally to keep the product constant.
Given Data / Assumptions:
 
Concept / Approach:
 Total man-days required = 10 * 8 = 80. Required men = total man-days / target days = 80 / 0.5.
Step-by-Step Solution:
 Total man-days = 80. Men needed in 0.5 day = 80 / 0.5 = 160.
Verification / Alternative check:
 Check proportionality: target time is 1/16 of 8 days; thus men must be 16 times 10, i.e., 160 men.
Why Other Options Are Wrong:
 80, 100, 120 do not satisfy 80 man-days when multiplied by 0.5 day.
Common Pitfalls:
 Misreading “half a day” as “half the days.” Here it explicitly means 0.5 day, not 4 days.
Final Answer:
 160
Discussion & Comments