Arun has completed
rd of the work in 8 days
Then he can complete the total work in
---- 8
1 ---- ?
= 24 days
But given Akhil is only 60% as efficient as Arun
Akhil =
Akhil can complete the total work in 40 days
Now, remaining 2/3rd of work can be completed in
1 ------ 40
------ ?
= 26.66 days.