Home » Aptitude » Time and Work

A and B together can do a piece of work in 36 days, B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in

← Previous Question Next Question→

Discussion & Comments

No comments yet. Be the first to comment!