A can lay a railway track in 16 days and B in 12 days. With help of C they finish the job in 4 days. In how many days can C alone do the job?
Aptitude
Time and Work
Difficulty: Easy
Choose an option
Answer
Correct Answer: 9⅕ days
Explanation
Problem restatementCompute C’s rate from the combined rate and A, B rates; then invert to get C’s solo time.
Given data
- A: 16 days ⇒ 1÷16 per day
- B: 12 days ⇒ 1÷12 per day
- A + B + C: 4 days ⇒ 1÷4 per day
Concept/ApproachUse linearity of rates: rC = rABC − rA − rB.
Step-by-step calculationrC = 1÷4 − 1÷16 − 1÷12= 12÷48 − 3÷48 − 4÷48 = 5÷48 per dayTime for C alone = 48÷5 = 9⅕ days (9.6 days)
Verification/AlternativeSum rates: 1÷16 + 1÷12 + 5÷48 = 3÷48 + 4÷48 + 5÷48 = 12÷48 = 1÷4.
Common pitfallsDo not average days; always add rates.
Final Answer9⅕ days