Equivalent work (man-hour balancing): 20 workers working 5 hours per day finish a job in 10 days. If instead 25 workers are employed for 10 hours per day, how many days will be required to complete the same job?

Aptitude Time and Work Difficulty: Easy
Choose an option
Answer

Correct Answer: 4 days

Explanation

Introduction / Context:With uniform productivity, total work is proportional to (workers × hours/day × days). Balance man-hours between the two scenarios to find the unknown days.

Given Data / Assumptions:

  • Scenario 1: 20 workers × 5 h/day × 10 days.
  • Scenario 2: 25 workers × 10 h/day × D days.

Concept / Approach:Set total man-hours equal between the two scenarios.

Step-by-Step Solution:Total (1) = 20 * 5 * 10 = 1000 man-hours.Let D be required days in scenario (2): 25 * 10 * D = 1000 ⇒ 250D = 1000 ⇒ D = 4.

Verification / Alternative check:Intuitively, scenario (2) has 2.5 times the daily man-hours (25 * 10 vs 20 * 5 = 250 vs 100), hence time shrinks by 1000/250 = 4 days.

Why Other Options Are Wrong:3, 5, 6, 8 days do not preserve equality of total man-hours for the same job.

Common Pitfalls:Comparing only workers or only hours per day without multiplying both.

Final Answer:4 days

Discussion & Comments
No comments yet. Be the first to comment!
Join Discussion