Work and Wages – B’s share when A and B finish together: Individually A needs 30 days and B needs 40 days to complete a job. They finish together and receive $2100. What is B’s share?
Aptitude
Work and Wages
Difficulty: Easy
Choose an option
-
A$900
-
B$1200
-
C$800
-
D$1300
-
E$750
Answer
Correct Answer: $900
Explanation
Introduction / Context:For constant-rate workers, wage shares are proportional to their work rates. Since both worked for the same time together, use rates directly to split the total payment.
Given Data / Assumptions:
- A’s time = 30 days ⇒ rate = 1/30
- B’s time = 40 days ⇒ rate = 1/40
- Total payment = $2100
Concept / Approach:Ratio A:B = (1/30):(1/40) = 40:30 = 4:3. Thus B’s share is 3/7 of the total.
Step-by-Step Solution:Total ratio parts = 4 + 3 = 7B’s share = 3/7 * 2100 = $900
Verification / Alternative check:A’s share = 4/7 * 2100 = $1200; together $2100.
Why Other Options Are Wrong:$1200 is A’s share; $800, $1300, and $750 do not equal 3/7 of $2100.
Common Pitfalls:Using time ratio 30:40 directly; always use rate ratio (reciprocals).
Final Answer:$900