A's 1 day's work = 1/15
B's 1 day's work = 1/20
C's 1 day's work = 1/25
A, B and C worked together.
∴ (A + B + C)'s 1 day's work = (1/15) + (1/20) + (1/25)
= (20 + 15 + 12)/ 300
= 47/300
Days taken to complete work by A, B and C working together = 300/47
∴ Share of C = (1/25) x (300/47) x 47000
= ₹ 1200