You have recently been promoted to a project manager for a clinical testing facility. The team is developing a new product that will cut down on testing interval requirements for a new seizure management medication. After you become involved with the project, you decide to add more research reports, which the customer did not request. This is an example of

Correct Answer: Gold Plating

Explanation:

Answer A is incorrect because you are providing a service that the customer did not request; therefore, it might not be important to her and unnecessary. Answer B is incorrect because scope creep is generally an expansion of the scope of the project at the customer's request and the customer did not request these reports. Answer C is incorrect because an additional report does not always mean increased diligence with a project.