A contractor planned to complete a job in 9 days. He hired a certain number of men. However, 6 of them were absent from day one, and the remaining men finished the job in 15 days. How many men had the contractor originally planned to employ?

Aptitude Time and Work Difficulty: Medium
Choose an option
Answer

Correct Answer: 15

Explanation

Introduction / Context:This question applies the person-days (or rate) method. If a contractor expects n men to finish in 9 days, the total work can be written as n * 9 in man-days. When only (n − 6) men actually work and the job takes 15 days, the same work is (n − 6) * 15 man-days. Equating these allows us to solve for n.

Given Data / Assumptions:

  • Planned workforce = n men.
  • Planned duration = 9 days.
  • Actual workforce = n − 6 men (from day one).
  • Actual duration = 15 days.
  • Per-man productivity is constant throughout.

Concept / Approach:Total work is invariant. Express it both ways and solve for n. Using person-days avoids needing the per-man rate explicitly; it cancels out naturally.

Step-by-Step Solution:

Planned work = n * 9.Actual work = (n − 6) * 15.Equate: n * 9 = (n − 6) * 15.Expand: 9n = 15n − 90 ⇒ 6n = 90 ⇒ n = 15.

Verification / Alternative check:If 15 men could finish in 9 days, but only 9 men (15 − 6) worked, the duration factor increases by 15/9 = 5/3; 9 * (5/3) = 15 days, consistent.

Why Other Options Are Wrong:6, 9, 12, 13 do not satisfy 9n = 15(n − 6); only n = 15 balances both sides.

Common Pitfalls:Confusing total work with rate; forgetting that fewer workers increase time proportionally; attempting to assign arbitrary per-man rates (unnecessary).

Final Answer:15

Discussion & Comments
No comments yet. Be the first to comment!
Join Discussion