36 men can finish a job in 18 days. In how many days will 27 men complete the same work (same efficiency)?
Aptitude
Chain Rule
Difficulty: Easy
Choose an option
-
A20 days
-
B21 days
-
C24 days
-
D30 days
-
ENone of these
Answer
Correct Answer: 24 days
Explanation
Concept / Approach
- Assuming equal efficiency, Work = Men × Days (constant for the same job).
Step-by-step calculation36 × 18 = 27 × DD = (36 × 18) ÷ 27 = (4/3) × 18 = 24
Quick checkFewer men (27 < 36) ⇒ more days; 24 > 18, consistent.
Final Answer24 days