P can complete the work in (12 x 8) hrs = 96 hrs
Q can complete the work in (8 x 10) hrs=80 hrs
Therefore, P's 1 hour work=1/96 and Q's 1 hour work= 1/80
(P+Q)'s 1 hour's work =(1/96) + (1/80) = 11/480. So both P and Q will finish the work in 480/11 hrs
Therefore, Number of days of 8 hours each = (480/11) x (1/8) = 60/11