In a garrison, there was food for 1000 soldiers for one month. After 10 days 1000 more soldiers joined the garrison How long would the soldiers be able to carry on with the remaining food?
A man and a boy working together can complete a work in 24 days. If for the last 6 days, the man alone does the work, then it is completed in 26 days. How long will the boy take to complete the work alone?
25 men can reap a field in 20 days. when should 15 men leave the work, if the whole field is to be reaped in 37 1/ 2 days after they leave the work?
If 12 men or 18 women can do a piece of work in 14 days, then how long will 8 men and 16 women take to finish the work?
When a 192 meters long rod is cut down into small pieces of length 3·2 meters each. Then how many pieces are available?
The cost of 2 tables is equal to the cost of 5 chairs. If the difference of the cost of one table and one chair is Rs. 1200, then the cost of one chair is —
If the cost of 1/4 th of kg is Rs. 0·60, then what is the cost of 200 gm ?
If the cost of 3 dozens mangoes is Rs. 245, what will be the approximate cost of 363 mangoes?
If the weight of 13 meters long rod is 23·4 kg. What is the weight of 6 meters long rod?
357 mangoes cost Rs. 1517·25, then what is the approximate cost of 49 dozen of mangoes?
Cost of 7000 bricks is Rs. 5740. Cost of luggage to carry the bricks to the building place is Rs. 805. What is the cost at per thousand bricks?
5 dozen toys are packed in a box and 98 boxes are kept in a tempo. How many tempos can lift 29400 toys in one round?
Cost of 1 dozen of bananas is Rs. 2·35, then what is the 4 approximate cost of 42 dozen of bananas?
Cost of 1 chair is Rs. 214 and cost of one table is Rs. 937, then what is the approximate cost of 6 dozen chairs and 4 dozen tables?
3 pumps, working 8 hours a day, can empty a tank in 2 days. How many hours a day should 4 pumps work in order to empty the tank in 1 day?
39 persons can repair a road in 12 days, working 5 hours a day. In how many days will 30 persons, working 6 hours a day, complete the work?
A contract is to be completed in 56 days if 104 persons work, each working at 8 hours a day. After 30 days, 25 % of the work is completed. How many additional persons should be deployed so that the work will be completed in the scheduled time, each person now working 9 hours a day.
'P' men working 'P' hours per day can do 'P' units of a work in 'P' days. How much work can be completed by 'Q' men working 'Q' hours per day in 'Q' days?
In a camp, there is a meal for 120 men or 200 children. If 150 children have taken the meal, how many men will be catered to with remaining meal?
10 men, working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the work in 12 days?