Seven spiders can weave seven complete webs in seven days. Assuming all spiders work at the same constant rate, in how many days will one spider weave one web?

Aptitude Chain Rule Difficulty: Easy
Choose an option
  • A
    1 day
  • B
    3 days
  • C
    7 days
  • D
    14 days
  • E
    21 days

Answer

Correct Answer: 7 days

Explanation

Introduction / Context:This question is a neat illustration of unitary method and work-rate reasoning. It appears simple at first glance but can be confusing if you only look at the numbers superficially. The key is to think in terms of total spider-days needed per web rather than trying to guess directly.

Given Data / Assumptions:- 7 spiders weave 7 webs in 7 days.- All spiders are equally efficient and work continuously at the same rate.- We want the time required for 1 spider to weave 1 web.

Concept / Approach:The best way to handle this is to calculate the total work and express it in spider-days. Then you can find how many spider-days are required to make a single web. Finally, you translate spider-days into days for one spider. Total work is measured in “webs”, while effort is measured in “spider-days”.

Step-by-Step Solution:Step 1: Compute total spider-days used in the given situation: 7 spiders * 7 days = 49 spider-days.Step 2: The result of this effort is 7 webs. So, 7 webs require 49 spider-days.Step 3: Therefore, 1 web requires 49 / 7 = 7 spider-days.Step 4: If 1 spider is working alone, each day contributes exactly 1 spider-day.Step 5: To accumulate 7 spider-days, one spider will need 7 days.Step 6: Hence, one spider will weave one web in 7 days.

Verification / Alternative check:You can also reason proportionally: the situation “7 spiders make 7 webs in 7 days” is symmetric. Intuitively, that means each spider effectively makes 1 web in 7 days, since there are 7 spiders and 7 webs. This matches the more formal spider-day calculation.

Why Other Options Are Wrong:1 day and 3 days are too short and would imply each spider makes multiple webs in 7 days, contradicting the original data. 14 or 21 days are too long and would give fewer than 7 webs in 7 days if all spiders were working at those speeds. Only 7 days is consistent with the total of 7 webs from 7 spiders in 7 days.

Common Pitfalls:Some learners misinterpret the statement and think “7 spiders, 7 webs, 7 days” automatically means 1 day for 1 web, forgetting that the work is shared. Others mix up proportionality, assuming work per spider per day is 1 web, which clearly contradicts the total. Using spider-days as a unit of effort helps avoid these errors.

Final Answer:One spider will make one web in 7 days.

Discussion & Comments
No comments yet. Be the first to comment!
Join Discussion