When preparing a detailed cost estimate for a civil project, which factors must be considered to ensure realistic rates and accurate quantities?

Difficulty: Easy

Correct Answer: All the above.

Explanation:


Introduction / Context:
Accurate estimates underpin budgeting, tendering, and cost control. Ignoring logistics or local labour markets can cause significant deviations between estimated and actual costs.



Given Data / Assumptions:

  • Project involves conventional civil works (earthwork, concrete, masonry, services).
  • Market conditions vary by location and time.



Concept / Approach:
A comprehensive estimate accounts for material quantities, their availability and lead times, transport distances and modes, and site-specific labour productivity and wage rates. These together determine item rates in the bill of quantities.



Step-by-Step Solution:
1) Quantify materials from drawings/specifications.2) Assess availability (local suppliers, seasonal constraints).3) Compute transport costs (quarry/plant to site), including handling and stacking.4) Apply local wage rates and productivity norms to labour components.



Verification / Alternative check:
Compare derived rates with schedule-of-rates and recent tender outcomes to validate.



Why Other Options Are Wrong:

  • Each factor is essential; omitting any leads to skewed rates.



Common Pitfalls:

  • Assuming uniform material availability across regions.
  • Underestimating transport for remote or urban-congested sites.



Final Answer:
All the above..

More Questions from Estimating and Costing

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion