Difficulty: Medium
Correct Answer: 60÷11 days (≈ 5.45 days)
Explanation:
Problem restatement
Normalize each worker’s productivity to an hourly rate, add them, then convert back to days at 8 hours per day.
Given data
Concept/Approach
Use hourly rates to combine fairly, since daily hours differ in the solo statements.
Step-by-step calculation
Combined hourly rate = 1÷96 + 1÷80 = (5 + 6)÷480 = 11÷480 per hourCombined daily rate at 8 h/day = 8 × 11÷480 = 11÷60 per dayDays required = 1 ÷ (11÷60) = 60÷11 days ≈ 5.45 days
Verification/Alternative
In 5.45 days at 8 h/day ≈ 43.6 h total; at 11÷480 per hour this gives about 1 unit of work.
Common pitfalls
Do not average 12 and 8 days; different daily hours make that invalid.
Final Answer
60÷11 days (≈ 5.45 days)
Discussion & Comments