Home » Aptitude » Time and Work

A can lay a railway track in 16 days and B in 12 days. With help of C they finish the job in 4 days. In how many days can C alone do the job?

Difficulty: Easy

Correct Answer: 9⅕ days

Explanation:

Problem restatement
Compute C’s rate from the combined rate and A, B rates; then invert to get C’s solo time.


Given data

  • A: 16 days ⇒ 1÷16 per day
  • B: 12 days ⇒ 1÷12 per day
  • A + B + C: 4 days ⇒ 1÷4 per day

Concept/Approach
Use linearity of rates: rC = rABC − rA − rB.


Step-by-step calculation
rC = 1÷4 − 1÷16 − 1÷12= 12÷48 − 3÷48 − 4÷48 = 5÷48 per dayTime for C alone = 48÷5 = 9⅕ days (9.6 days)


Verification/Alternative
Sum rates: 1÷16 + 1÷12 + 5÷48 = 3÷48 + 4÷48 + 5÷48 = 12÷48 = 1÷4.


Common pitfalls
Do not average days; always add rates.


Final Answer
9⅕ days

← Previous Question Next Question→

More Questions from Time and Work

Discussion & Comments

No comments yet. Be the first to comment!
Join Discussion