Difficulty: Easy
Correct Answer: 13⅓ days
Explanation:
Problem restatement
Determine individual rates from the partial schedule, then compute their combined time for the entire work.
Given data
Concept/Approach
Compute the remaining fraction after X works, deduce Y’s rate, then add rates to find combined time.
Step-by-step calculation
Work done by X in 8 days = 8 ÷ 40 = 1÷5Remaining work = 1 − 1÷5 = 4÷5Y does 4÷5 in 16 days ⇒ Y’s rate = (4÷5) ÷ 16 = 1÷20 per dayCombined rate = 1÷40 + 1÷20 = 3÷40 per dayTime together = 1 ÷ (3÷40) = 40÷3 = 13⅓ days
Verification/Alternative
Rates are consistent with the given completion periods for X and Y individually.
Common pitfalls
Do not average days; always add rates.
Final Answer
13⅓ days