Curioustab
Aptitude
General Knowledge
Verbal Reasoning
Computer Science
Interview
Aptitude
General Knowledge
Verbal Reasoning
Computer Science
Interview
Time and Work Questions
If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:
Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is:
A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?
A, B and C can complete a piece of work in 24, 6 and 12 days respectively. Working together, they will complete the same work in:
A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:
A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?
A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?
A and B can together finish a work 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days A alone can finish the work?
A man, on tour travel first 160 km, at 64 km/hr. and the next 160km at 80km/hr. the average speed for the first 320 km. of the tour is?
By walking at 3/4 of his usual speed, a man reaches his office 20 minute later than usual. this usual time is?
A man travels 35 km partly at 4 km/hr and at 5 km/hr. If he covers former distance at 5 km/hr and later distance at 4 km/hr, he could cover 2 km more in the same time. The time taken to cover the whole distance at original rate is
6 men or 10 women can reap a field in 15 days, then the number of days that 12 men and 5 women will take to reap the same field is :
6 children and 2 men complete a certain piece of work in 6 days. Each child takes twice the time taken by a man to finish the work. In how many days will 5 men finish the same work?
2 men or 5 women or 7 boys can finish a work in 469 days, then the number of days taken by 7 men, 5 women and 2 boys to finish the work is :
314 weavers weaves 6594 shawls in 1/6 hours. What is the number of shawls weaved per hour by an average weaver?
The Ratio of efficiencies of A, B and C is 6 : 5 : 4 and if A, B and C received total Rs. 27000 for the whole work. What is the share of C, if the money is distributed in the ratio of amount of work done, individually?
If 2 men or 3 women or 4 boys can do a piece of work in 52 days. Then the same piece of work will be done by 1 man, 1 woman and 1 boy in?
A contractor undertook a work to complete in 60 days. But just after 20 days he observed that only 1/5th of the project work had been completed. To complete the work in time (i.e,In rest days) minimum how many workers he had to increase, if there were initially 75 workers were deployed for the task?
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28