Time and Work Questions

Practice Time and Work MCQs with answers and explanations. Page 2 of 27.

Category
Aptitude
Topic
Time and Work
Page
2 / 27
Mode
Practice

Questions

Open any question to view the answer and explanation.

6 men + 8 boys finish a job in 10 days; 26 men + 48 boys finish the same job in 2 days. In how many days will 15 men + 20 boys finish it?
Open
View answer
Sakshi can finish a job in 20 days. Tanya is 25% more efficient than Sakshi. In how many days can Tanya finish the same job?
Open
View answer
A finishes a work in 18 days, B in 15 days. B works for 10 days and leaves. In how many days will A alone finish the remaining work?
Open
View answer
A and B together finish a job in 30 days. A works alone for 16 days; B then finishes the remainder alone in 44 days. In how many days can B alone finish the whole job?
Open
View answer
A, B, C can complete a work in 24, 6, and 12 days respectively. Working together, how long will they take to complete the work?
Open
View answer
A can finish a job in 24 days, B in 9 days, and C in 12 days. B and C work together for 3 days; A completes the remainder. How many days does A take for the remainder?
Open
View answer
A alone can do a job in 4 hours; (B + C) together in 3 hours; (A + C) together in 2 hours. How long will B alone take?
Open
View answer
A completes 80% of a work in 20 days. A and B together finish the remaining work in 3 days. How long would B alone take to do the whole work?
Open
View answer
A is 30% more efficient than B. If A alone can complete a job in 23 days, how long will A and B together take to finish it?
Open
View answer
A and B can complete a work together in 30 days. They work together for 20 days; then B leaves, and A finishes the remaining work in the next 20 days. In how many days can A alone finish the work?
Open
View answer
By walking at only three-fourths (3/4) of his usual speed, a person reaches his office 20 minutes later than he normally does. What is his usual (normal) time to cover the same route?
Open
View answer
A man travels a total of 35 km partly at 4 km/h and partly at 5 km/h. If he instead travels the earlier portion at 5 km/h and the later portion at 4 km/h, he could cover 2 km more in the same total time. Find the original total time taken.
Open
View answer
Six men or ten women can reap a field in 15 days. How many days will it take for a team of 12 men and 5 women to reap the same field?
Open
View answer
Six children and two men complete a job in 6 days. Each child takes twice as long as a man to finish the work alone (i.e., a child is half as efficient as a man). In how many days can five men alone finish the same work?
Open
View answer
Two men or five women or seven boys can finish a work in 469 days. In how many days will seven men, five women, and two boys together finish the same work?
Open
View answer
A total of 314 weavers weave 6594 shawls in one-sixth (1/6) of an hour (i.e., 10 minutes). On average, how many shawls does one weaver weave per hour?
Open
View answer
The efficiencies (work rates) of A, B, and C are in the ratio 6 : 5 : 4. If they receive a total of ₹ 27000 for completing the job and payment is distributed in proportion to individual work done, what is C’s share?
Open
View answer
If two men or three women or four boys can complete a job in 52 days, then how many days will one man, one woman, and one boy together take to complete the same job?
Open
View answer
A contractor planned to finish a project in 60 days. After 20 days, only one-fifth (1/5) of the work was completed with 75 workers employed. To finish on time, how many additional workers are required for the remaining 40 days (assume output is proportional to workforce)?
Open
View answer
Twenty persons complete one-third (1/3) of a job in 12 days. How many additional persons are needed to complete the remaining work in the next 12 days (assume equal efficiency)?
Open
View answer

Practice smarter

Solve a few questions daily and revisit weak topics regularly to improve accuracy.