Man-days scaling to a fraction of a day:
10 men can build a wall in 8 days. How many men are required to complete the same work in half a day (assume identical efficiency)?
Open
View answer
Mixed workforce (men and women):
3 men can finish a job in 6 days and 5 women can finish the same job in 18 days. If 4 men and 10 women work together, how many days will they require to finish the job?
Open
View answer
Men and children together:
3 men can do a work in 18 days; 6 children can do the same work in 18 days. How many days will 4 men and 4 children together need to finish the work?
Open
View answer
Three-person collaboration:
P can do a work in 12 days, Q alone in 8 days, and with the help of R they finish in 4 days. How many days would R alone take to complete the work?
Open
View answer
Staggered start in work:
A alone can finish a job in 15 days, and B alone can do it in 10 days. A starts the work and B joins after 5 days. For how many total days did the work last until completion?
Open
View answer
Efficiency comparison:
A does 20% less work than B (i.e., A’s rate is 20% lower). If A can complete the job in 7.5 hours, in how many hours can B complete the same job?
Open
View answer
Relative efficiency increase:
X can complete a work in 16 days. If Y’s efficiency is 60% more than X’s efficiency, in how many days can Y complete the same work?
Open
View answer
Men and women together with partial information:
2 men and 3 women finish 25% of a job in 4 days. Also, 6 men and 14 women finish the whole job in 5 days. In how many days will 20 women finish the entire work?
Open
View answer
Determine a woman’s solo time from a mixed team:
10 men and 15 women finish a work in 6 days. One man alone can finish the same work in 100 days. In how many days can one woman alone finish the work?
Open
View answer
Share in contract work:
A, B and C contract to complete a work for Rs. 550. Together A and B are supposed to do 7/11 of the work. What should be C’s share of the payment?
Open
View answer
Time and Work — Individual vs. Combined Rates
A can complete the work alone in 6 days, and B can complete the same work alone in 3 days.
If A and B work together from start to finish, in how many days will they complete the entire work?
Open
View answer
Work Rates — Isolating One Worker's Time from Group Data
Ram, Dilip, and Shekhar together complete a job in 20 days. Ram and Dilip together complete the same job in 30 days.
How many days would Shekhar alone take to complete the job?
Open
View answer
Three Workers with Different Efficiencies
Sunil completes the work in 4 days, Dinesh in 6 days, and Ramesh works 1.5 times as fast as Sunil.
If all three work together from the start, how many days are required to finish the work?
Open
View answer
Staggered Start — One Worker Joins Later
Mahesh and Umesh can complete a job in 10 days and 15 days, respectively. Umesh works alone for the first 5 days, after which Mahesh also joins.
In how many total days is the work completed?
Open
View answer
Two Workers — Partial Contribution Then Solo Finish
A can do the work in 80 days. He works alone for 10 days, and then B alone finishes the remaining work in 42 days.
If A and B worked together from the start, in how many days would they finish?
Open
View answer
Staggered Collaboration — B Joins After 10 Days
A can complete a job in 25 days and B can complete it in 20 days. A starts alone and B joins after 10 days.
What is the total duration of the work (in days)?
Open
View answer
Team Size Changes Midway
14 men can complete a work in 12 days. After 4 days, 2 more men join.
How many additional days are needed to complete the remaining work?
Open
View answer
Mid-Project Replacement and Net Team Size
12 men can finish a job in 9 days. After 3 days, 6 men join to replace 2 men (net change in team size).
How many more days are needed to finish the remaining work?
Open
View answer
Three People Working Together
A can do a job in 8 days, B can do it in 16 days, and C can do it in 80 days.
If all three work together, how many days are needed to complete the work?
Open
View answer
Classic Pair-Work Problem
A can do a piece of work in 10 days and B can do it in 15 days.
If they work together from start to finish, in how many days will they complete the work?
Open
View answer