Time and Work Questions
Practice Time and Work MCQs with answers and explanations. Page 21 of 27.
Category
Aptitude
Topic
Time and Work
Page
21 / 27
Mode
Practice
Questions
Open any question to view the answer and explanation.
S, T, and U can complete a piece of work in 40 days, 48 days, and 60 days respectively. They start the work together and receive Rs 10800 in total for completing it. T leaves 2 days before completion and U leaves 5 days before completion, so S alone finishes the remaining work. What is the share of S (in rupees) from the total payment?
Open
View answer
Ram and Hari together can cut 12 kilograms of nuts in 2 days. They work together for 5 days, after which Hari leaves and Ram alone takes 8 more days to cut the remaining nuts. If the total quantity of nuts cut is 58 kilograms, how much time (in days) would Hari alone take to cut 10 kilograms of nuts?
Open
View answer
Pannalal completes one-third of a job in 20 days. Saiprasad completes the remaining two-thirds of the same job in 10 days. In how many days can Pannalal and Saiprasad together complete the entire job if they work simultaneously from the start?
Open
View answer
P and Q can complete a project in 6 days and 12 days respectively when working alone. If P and Q work together, in how many days will they complete 25% of the entire project?
Open
View answer
Ranjith can complete a task in 25 days while Anji can finish the same task in 20 days. They work together on the task for 5 days, after which Ranjith leaves. In how many additional days will Anji alone finish the remaining work?
Open
View answer
Ganesh, Ram, and Sohan together can complete a piece of work in 16 days. Ganesh and Ram together can complete the same work in 24 days. How many days will Sohan alone take to finish the entire work?
Open
View answer
Nirmit can complete two-thirds of a job in 18 days. Kashish is twice as efficient as Nirmit. In how many days will Kashish alone complete the entire job?
Open
View answer
Sandy and Mandy together complete eight-thirteenths (8/13) of a job, and the remaining work is completed by Andy alone. If the total payment for the job is Rs 2600 and the workers are paid in proportion to the amount of work done, what is Andy's share in rupees?
Open
View answer
Three men or four women can complete a job in 120 days. If a team of 12 men and 16 women work together on the same job, in how many days will they complete it?
Open
View answer
A can complete a piece of work in 6 days working 8 hours per day, while B can complete the same work in 4 days working 10 hours per day. If A and B work together and the work must be finished in 5 days, how many hours per day should they work together?
Open
View answer
A and B together complete three fifths of a piece of work and C alone completes the remaining part. If A, B and C receive a total payment of Rs 5000 for the entire job, what is the share of C?
Open
View answer
Tushar can complete a piece of work in 6 hours and Amar can complete the same work in 10 hours. If both of them work together on the entire job, how much time will they take to finish it?
Open
View answer
Worker A can make a cupboard in 10 days and worker B can make it in 50 days. Together with a third worker C, they finish making one cupboard in 6.25 days. In how many days can C alone make the cupboard?
Open
View answer
Two labourers A and B together earn Rs 750 per day. If A is paid 150 percent of the daily wage paid to B, how much is B paid per day in rupees?
Open
View answer
Workers A and B together can finish a job in 12 days, while A alone can finish the same job in 20 days. If B works alone on the job, how many days will B take to complete it?
Open
View answer
Workers X, Y and Z can complete a certain piece of work in 30, 40 and 50 days respectively. All three start together, but Y leaves 4 days before the work is finished. In how many days in total is the work completed?
Open
View answer
Workers P, Q and R together can make one table in 40 minutes, while P and Q together can make the same table in 60 minutes. How many minutes will R alone take to make one table?
Open
View answer
A can finish a piece of work in 12 days and B can finish the same work in 24 days. If A and B work together on the job for 4 days, what fraction of the total work remains unfinished?
Open
View answer
Akash is three times as efficient a workman as Baldev and therefore finishes a certain job in 40 days less than Baldev. If they work together on the same job, in how many days will they complete it?
Open
View answer
Twenty eight women can complete a certain piece of work in 36 days. If 4 women leave after working for 18 days, how many additional days will be needed to finish the remaining work?
Open
View answer
Practice smarter
Solve a few questions daily and revisit weak topics regularly to improve accuracy.