Time and Work Questions
Practice Time and Work MCQs with answers and explanations. Page 7 of 27.
Category
Aptitude
Topic
Time and Work
Page
7 / 27
Mode
Practice
Questions
Open any question to view the answer and explanation.
Three workers with different capacities:
“A” can complete the job in 2 hours. “B” can do three times this job in 8 hours (i.e., rate = 3 jobs in 8 h). “C” can complete the same job as A in 8 hours. If all three work together on one job, how long will they take?
Open
View answer
Equivalent efficiencies for man, woman, and boy:
One man or two women or three boys can complete a job in 88 days. If one man, one woman, and one boy work together, in how many days will they finish the job?
Open
View answer
Time relations relative to the team:
A alone takes 25 days more than (A + B) together, and B alone takes 49 days more than (A + B) together. How many days do A and B together take to finish the work?
Open
View answer
Who is fastest given partial-work times:
X can do 1/4 of the work in 10 days, Y can do 40% of the work in 40 days, and Z can do 1/3 of the work in 13 days. If they work individually, who will finish the whole work first?
Open
View answer
One leaves after partial teamwork:
P and Q together can finish a work in 30 days. They work together for 10 days and then Q leaves. If P finishes the remaining work alone in 20 more days, how long would P take to complete the whole work alone?
Open
View answer
One worker leaves midway; other completes:
A can do a job in 60 days and B in 75 days. They begin together, but after some days A leaves and B finishes the remaining work in 30 days. After how many days from the start did A leave?
Open
View answer
More workers reduce the days:
20 women can complete a piece of work in 7 days. If 8 more women are added (i.e., total 28 women), in how many days will they finish the work?
Open
View answer
Changing the workforce size:
12 men can finish a piece of work in 24 days. If only 8 men are assigned, how many days will they need to complete the same work (assume equal efficiency)?
Open
View answer
Output changes with manpower and time:
20 men can cut 30 trees in 4 hours. If 4 men leave (so 16 men remain), how many trees will be cut in 12 hours by the remaining men (assume proportional output)?
Open
View answer
Scaling wall construction with men, length, and hours:
40 men build a 200 m wall in 12 days working 8 h/day. How many days will 30 men take to build a similar 300 m wall working 6 h/day (assume proportional productivity)?
Open
View answer
If m men, working m hours per day, can complete exactly m units of work in m days, then in n days how many units of work will be completed by n men working n hours per day? (Assume work ∝ men * hours/day * days and the same job type.)
Open
View answer
Twenty men complete one third of a job in 20 days. How many additional men must be employed so that the remaining two thirds of the job is finished in 25 more days?
Open
View answer
Forty five people dig a pond in 18 days. If the pond must be dug in 15 days, how many people are required?
Open
View answer
Three men or four women can build a wall in 43 days. In how many days can seven men and five women build the same wall?
Open
View answer
A and B together take 18 days to finish a job, B and C take 24 days, and C and A take 36 days. In how many days can A, B, and C together finish the job?
Open
View answer
A and B can do a job in 72 days, B and C in 120 days, and A and C in 90 days. In how many days can A alone finish the job?
Open
View answer
Twenty five men can reap a field in 20 days. If 15 men leave after some days and the field must then be finished in 37.5 days from that leaving point, after how many days should the 15 men leave?
Open
View answer
A can do a job in 5 hours, B in 9 hours, and C in 15 hours. If C works with A and B for only 1 hour, how much additional time will A and B together take to finish the remaining work?
Open
View answer
A alone can finish a job in 24 days, and B alone in 16 days. Working together with C, they finish the job in 8 days. In how many days can C alone finish the job?
Open
View answer
A can do a job in 10 days. B is 60 percent more efficient than A. In how many days can B alone complete the same job?
Open
View answer
Practice smarter
Solve a few questions daily and revisit weak topics regularly to improve accuracy.