Time and Work Questions

Practice Time and Work MCQs with answers and explanations. Page 9 of 27.

Category
Aptitude
Topic
Time and Work
Page
9 / 27
Mode
Practice

Questions

Open any question to view the answer and explanation.

Building vs. breaking: net progress with an interrupter A can build a structure in 8 days, while B can demolish the same structure in 3 days. A works alone for 4 days, then B joins and they work together for 2 days. After that, in how many days will A alone build the remaining structure?
Open
View answer
Catching up to a wall-length target with added manpower A 1000-meter wall must be built in 50 days. 56 men are hired, but after 27 days only 448 meters are completed. How many additional men must be employed to finish the remaining work on time?
Open
View answer
Inferring individual copy speed from a joint throughput Mr. Modi can copy 40 pages in 10 minutes. Together, Mr. Xerox and Mr. Modi copy 250 pages in 25 minutes. How many minutes will Mr. Xerox alone take to copy 36 pages?
Open
View answer
Mixed-team productivity then women-only completion Twenty-five men and fifteen women can complete a job in 12 days. All begin together; after 8 days the women stop. The remaining work is finished by 25 men in 6 days. How long would it take if only 15 women worked from start to finish?
Open
View answer
AB work 3 days; C is faster than (A+B) together by a factor of time A can do a job in 12 days, B in 8 days. C can do the same job in four-fifths of the time required by (A and B together). A and B work together for 3 days, then C alone completes the remainder. For how many days did C work?
Open
View answer
One-day head start by A, then both finish the job A completes a work in 15 days and B in 20 days. A works alone for 1 day, then A and B work together to finish. How many additional days are needed after the first day?
Open
View answer
A leaves mid-way; B finishes the remainder A can do a job in 10 days and B in 20 days. They start together, but after 5 days A leaves. In how many days will B complete the remaining work?
Open
View answer
Revised crew after day 3: how long to finish? Twelve men can complete a work in 8 days. After 3 days, three more men join the team. In how many days will they complete the remaining work?
Open
View answer
B and C start; A finishes after they leave A can complete a job in 9 days, B in 10 days, and C in 15 days. B and C work together for 2 days and then leave. How long will A take to finish the remaining work?
Open
View answer
Convert women to man-equivalents to size the final push Twenty-four men complete a job in 16 days. Thirty-two women can complete the same job in 24 days. Sixteen men and sixteen women work together for 12 days. How many more men must be added to finish the remaining work in 2 days (with the women continuing)?
Open
View answer
Three typists A, B, and C work on the same report. A alone can finish the report in 16 hours; B alone in 20 hours; C alone in 24 hours. All three start typing together at 9:00 a.m. At exactly 1:00 p.m. (after 4 hours), typist A stops and leaves the task. B and C continue and finish the remaining work together. Approximately at what time (clock time) is the report fully typed?
Open
View answer
A team of 14 persons can complete a job in 16 days (uniform productivity). Initially, 8 persons start the work and continue for 12 days. After 12 days, 8 more persons join (so the team becomes 16 persons). How many days will the team take to complete the remaining work after the new members join?
Open
View answer
Rates of men and boys in reaping hectares are different. If 5 men and 3 boys together reap 23 hectares in 4 days, and 3 men and 2 boys reap 7 hectares in 2 days, then how many boys must assist 7 men so that 45 hectares are reaped in 6 days?
Open
View answer
A piece of work was planned to finish in 40 days. The initial team managed to complete only half the work in 24 days. Then, 16 more men were added to the team, and the whole work was still finished exactly in the scheduled 40 days. How many men were employed at first?
Open
View answer
Workers A, B, and C can complete a job at different individual times. A alone takes 10 days; B alone takes 24 days. When A, B, and C work together, they finish the job in 6 days. In how many days can C alone complete the job?
Open
View answer
Production is proportional to men × hours × days. If 15 men make 12 toys by working 5 hours per day for 16 days, in how many days can 10 men make 15 toys by working 8 hours per day (same productivity per man-hour)?
Open
View answer
In a garrison, food was stocked for 1000 soldiers for one month (assume 30 days of rations). After 10 days, 1000 more soldiers joined (so total becomes 2000). For how many additional days will the remaining food last after the reinforcements arrive?
Open
View answer
Workers A and B can complete a job individually in 8 hours and 12 hours, respectively. If they work in alternate one-hour turns, starting with A, at what time (duration) will the job be completed?
Open
View answer
A contractor planned to complete a job in 9 days. He hired a certain number of men. However, 6 of them were absent from day one, and the remaining men finished the job in 15 days. How many men had the contractor originally planned to employ?
Open
View answer
Two inlet pipes A and B can fill a tank in 40 minutes and 60 minutes, respectively. An outlet pipe C empties the tank. With all three pipes open together, the tank fills in 30 minutes. How long would C alone take to empty a full tank?
Open
View answer

Practice smarter

Solve a few questions daily and revisit weak topics regularly to improve accuracy.