Time and Work Questions
Practice Time and Work MCQs with answers and explanations. Page 27 of 27.
Category
Aptitude
Topic
Time and Work
Page
27 / 27
Mode
Practice
Questions
Open any question to view the answer and explanation.
Working together, A, B, and C can complete a task in 12 days. If A alone can complete the task in 55 days and B alone can complete the task in 66 days, then in how many days can C alone complete the same task?
Open
View answer
A is three times as productive as C. Together, A and C can complete a job in 22.5 days. They work together for 15 days and then B joins them. If B alone can complete the entire job in 15 days, in how many additional days after B joins will the remaining work be finished?
Open
View answer
A can complete a piece of work in 16 days and B can complete the same work in 20 days. If they work together on this work for 8 days and then stop, what fraction of the total work will still remain to be completed?
Open
View answer
A can paint a house in 45 days and B can paint the same house in 15 days. Along with a third painter C, they can finish the painting in 5 days. If C worked alone from start to finish, in how many days would C be able to paint the entire house?
Open
View answer
Manjeet can complete a certain piece of work in 18 hours. Jaya is 100 percent more efficient than Manjeet, which means Jaya can work at twice Manjeet's rate. If both of them work together on this task, in how many hours will they finish the work?
Open
View answer
A group of carpenters promised to finish a job in 15 days. However, 3 of the carpenters were absent from the beginning, and the remaining carpenters actually took 20 days to complete the job. Based on this information, what was the original number of carpenters in the group?
Open
View answer
P and Q can complete a certain project in 150 days and 100 days respectively when working alone. If both P and Q work together on the project, in how many days will they complete 60 percent of the project?
Open
View answer
Azhar is four times as good a workman as Balaraj and therefore Azhar can finish a job in 45 days less than Balaraj takes to finish the same job alone. If Azhar and Balaraj work together, in how many days will they complete the job?
Open
View answer
Sister can bake 50 cakes in 25 hours. Sister and her mother together can bake 75 cakes in 15 hours. Based on this time and work information, how many cakes can the mother (Mummy) bake alone in 15 hours?
Open
View answer
A does 50 percent of a certain piece of work in 12 days. He then calls in B and together they finish the remaining half of the work in 8 days. If the total work is considered as one complete job, how long would B alone take to complete the entire work?
Open
View answer
Parimal completes one fourth of a certain job in 10 days. Salim completes the remaining three fourths of the same job in 20 days. If both Parimal and Salim work together from the beginning, in how many days can they finish the entire job?
Open
View answer
Abhinav is twice as efficient a workman as Balwant and therefore completes a certain job in 36 days less than Balwant. If both Abhinav and Balwant work together on this job, in how many days will they complete it?
Open
View answer
Working together, A and B can complete a certain job in 40 days, B and C can complete the same job in 36 days, and A, B and C together can complete it in 24 days. Based on this time and work data, in how many days can B alone finish the entire job?
Open
View answer
A, B and C can do a certain job working alone in 50 days, 75 days and 20 days respectively. They all work together on the job for 4 days, after which C leaves. For the remaining work, only A and B continue. How many additional days will A and B together take to finish the rest of the job?
Open
View answer
A can complete 50 percent (one half) of a job in 16 days, while B can complete one fourth of the same job in 24 days. If A and B work together from the start, in how many days can they complete three fourths of the job?
Open
View answer
A and B can together complete a certain task in 18 hours. After working together for 6 hours, A leaves and B alone takes another 36 hours to complete the rest of the task. In how many hours would A alone complete the entire task if he worked by himself from the beginning?
Open
View answer
Practice smarter
Solve a few questions daily and revisit weak topics regularly to improve accuracy.